Click here to make tpub.com your Home Page

Page Title: Reconditioning of Initial Production Test Sample
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 




img
MIL-N-81497A(AS)
Reconditioning of Initial Production Test Sample -
4.3.4
On completion of the initial production test the equipment shall
be reworked by the contractor by replacing all worn or damaged items.
After reworking, the contractor shall resubmit the equipment for
acceptance.
Acceptance Tests - The contractor shall furnish all
4.4
samples and shall be responsible for accomplishing the acceptance
tests. All inspection and testing shall be witnessed by the
procuring activity if desired. Contractors not having testing facili-
ties satisfactory to the procuring activity shall engage the service
of a commercial testing laboratory acceptable to the procuring activi-
ty. The contractor shall furnish test reports showing quantitative
results for all acceptance tests. Such reports shall be signed by
an authorized representative of the contractor or laboratory, as
applicable. Acceptance or approval of material during the course of
manufacture shall not be construed as a guarantee of the acceptance
of the finished product. Acceptance tests shall consist of the following:
(1) Individual Tests
Sampling Tests
(2)
Reliability Assurance Tests
(3)
(4)
Special Tests
Individual Tests - Each equipment submitted for
4.4.1
acceptance shall be subjected to the individual tests. These tests
shall be adequate to determine compliance with the requirements of
material, workmanship, operational adequacy and reliability. As a
minimum, each equipment accepted shall have passed the following
tests:
(1) Examination of Product
(2) Operational Test
(3) Manufacturing Run in Test
Examination of Product - Each equipment shall be
4.4.1.1
examined carefully to determine that the material and workmanship
requirements have been met.
55