MIL-T-18232B(AS)
3.1.15
SECTIONALIZATION - Targets designed for use
aboard ships
shall be capable of being disassembled
into components suitable for transport through rectangular openings whose limit-
ing dimensions are 48 inches wide by 39 inches high onto elevator platforms
9'-0" x 4'-0". Assembled targets shall be capable of being transported through
rectangular openings whose limiting dimensions are 60 inches wide by 39 inches
high onto elevator platform 14'-6" x 5'-6". Transporting trucks or dollies shall
be included in clearances specified above. Detachment of minor, quickly assembled
structural components to achieve this capability is permitted. Whenever possible
the disassembled parts shall be capable of being handled and stowed on pallets
with the following characteristics:
Each unit 4 ft. long by 4 ft. wide
Height - should be equal division of 7 ft as this iS
working headroom aboard ship (e.g. 3 1/2 ft., 1 3/4 ft.
etc.)
Max. wt. per Unit - 2800#
READINESS. - The target shall be designed to have the least
3.3.16
possible test or checkout after delivery. Unless otherwise
specified in the detail specification, the target shall have the following per-
formance with regard to readiness:
(1) Ready storage checkout. - Using related standard and/or
specialized test equipment and support equipment, the time
to prepare the target for checkout, to perform the checkout and to restore the
target to launcher-installation readiness condition, shall not exceed 30 minutes,
exclusive of time required to remove the target and/or sections from either
packaged or unpackaged storage. The average time required to perform the check-
out shall not exceed 10 minutes per target. The target shall maintain full
effectiveness in the ready storage condition without requiring further checkout
for a period of not less than two days.
(2) Installation on Launcher. - The target, having  undergone
ready storage checkout, shall be capable of undergoing
preflight servicing and launcher installation in a time period not to exceed 20
minutes by three men utilizing related standard and/or specialized support
equipment. Full effectiveness shall be maintained for eight hours following
preflight servicing.
(3) Flight readiness. - Hating undergone pre-flight servicing,
the target shall be capable of being brought to warmed-up
ready-to-launch condition within ten minutes after power is applied to target.
With power applied the target shall be capable of maintaining this warmed-up,
ready-to-launch condition as specified in the detail specification.
13