Page Title: Responsibility for compliance
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 




img
MIL-T-62735
his own or any other facilities suitable for the performance of the inspection requirements
specified herein, unless disapproved by the Government. The Government reserves the right to
perform any of the inspections set forth in the specification where such inspections are deemed
necessary to assure supplies and services conform to prescribed requirements.
4.1.1 Responsibility for compliance. All items must meet all requirements of sections 3
and 5. The inspection set forth in this specification shall become a part of the contractor's overall
inspection system or quality program. The absence of any inspection requirements in the
specification shall not relieve the contractor of the responsibility for ensuring that all products or
supplies submitted to the Government for acceptance comply with all requirements of the
contract. Sampling inspection, as part of manufacturing operations, is an acceptable practice to
ascertain conformance to requirements, however, this does not authorize submission of known
defective material, either indicated or actual, nor does it commit the Government to acceptance
of defective material.
4.2 Government verification. Quality assurance operations performed by the contractor
will be subject to Government verification at unscheduled intervals. Verification will consist of
observation of the operations to determine that practices, methods, and procedures of the
contractor's inspection are being properly applied. Failure of the contractor to promptly correct
product deficiencies discovered shall be cause for suspension of acceptance until correction has
been made or until conformance of product to specification criteria has been demonstrated.
4.3 First production vehicle inspection. The first vehicle produced under the contract
shall be inspected by the contractor under the direction and in the presence of Government
representatives. The purpose of the inspection shall be to determine vehicle conformance to the
contract. Acceptance of the first production vehicle shall not constitute a waiver by the
Government of its rights under the provisions of the contract.
4.3.1 Vehicle weight. The first production vehicle shall be weighed to determine the
curb weight and distribution of the curb weight on the front and rear axles. The total imposed
loads on the front and rear axles shall be computed by the contractor and verified by the
Government, using the curb weight, the operator weight at 80 kg (175 pounds), and the payload
required to provide the specified GVW. Except as specified in 3.1.7.1, the calculated imposed
loads on the front and rear axles, shall be compared to their suspension, axle and tire load
capacity ratings to determine if these components are of adequate capacity to meet contractual
requirements. See 6.4.
62