| MIL-C-45975B(AR)
6.2.1 Acquisition requirements. Acquisition documents should specify the
following:
a.
Title, number, and date of this specification.
b.
Requirements for and the number of cannon, components thereof, or both to
be submitted for first article by the contractor (see 3.2),
c.
The examinations and tests to be performed by the contractor and the
examinations and tests to be performed by the Government.
d.
All inspection and test data that is required.
e.
At whose expense a retest may be performed.
f.
Serial numbers for the cannon and repair tube assemblies.
g.
Inspection equipment, responsibility for acquisition, maintenance, and
disposition thereof, if other than as specified (see 4.7.3).
h.
Availability of inspection equipment from the Government.
i.
Extent of supplier's responsibility for Government furnished and for
supplier-required final inspection equipment.
j.
Applicable acceptance test procudcers
k.
When a proof firing sampling plan is authorized, the proof firing
sampling plan parameters: initial consecutive quantity (i), and sampling
frequency (f) (see 4.7.6.1.2).
l.
Under what conditions simulated firing may be performed, the test
equipment available, and the procedures to be followed.
m.
The levels of preservation, packaging, and packing required for cannon
assemblies (see 5.1) and repair parts (see 5.2)
n.
When applicable, bar code marking requirements (see 5.3).
o.
When warranted, the application of MIL-Q-9858 or MIL-I-45208, as
appropriate.
p. Unless otherwise specified, the application of MIL-I-45607 and
MIL-STD-45662.