4.4.2 Examination. See MIL-A-48078. Conditioning shall
be at 23 2C and 50 5% R.H. for a minimum of four hours.
These conditioning requirements apply to container assembly
sample inspections (paragraph 4.4.2.5) that require gaging.
Unless otherwise specified in the Classification of Defects and
Test tables, sampling plans for major and minor defects shall
be in accordance with MIL-STD-105, Inspection Level II.
4.4.2.1 Mold examination and process requirements.
4.4.2.1.1 Qualification for new or rework die-press
set-ups. Qualification of new or reworked die-press setups
shall be in accordance with 4.3.4.
4.4.2.1.2 Process requirements. Homogeneity inspection
will be performed prior to assembly of container halves.
|