| ![]() MIL-D-70603(AR)
The first article sample shall be evaluated in accordance with
the provisions of 4.3.2 and 4.3.3. Unless otherwise directed by the
Contracting Officer, loaded components shall not be submitted to a
Proving Ground for any test until the above assemblies submitted in
accordance with this paragraph have been accepted.
See MIL-A-48078 and Table I
4.3.2 Inspections to be performed.
specified herein. If any items fail to comply with any of the
applicable requirements, the first article sample shall be rejected.
4.3.3 Rejection.
MIL-A-48078 shall apply with the exception
that the first article sample shall be rejected if five (5)
detonators fail either functioning/waterproof test as specified.
|