| MIL-E-63300A(AR)
4.5.19 Quality assurance soldering plan. The QA soldering plan
as noted in 3.3.2 shall be submitted to the Government. (see 6.5).
(Ref. DI-T-5372 (tailored)).
4.5.20 Data requirements. The contractor shall submit a
quality inspection test, demonstration and evaluation report in
accordance with Data Item Description DI-R-1724 (tailored). It
shall include all detailed inspection and test results. Test data
reports shall be submitted to the technical agency listed in 6.5.
4.5.21 Variables data. The contractor shall submit variables
data in accordance with Data Item Description DI-R-1724 (tailored)
for the first article samples. It shall include all detailed
inspection and test results with respect to the following
parameters: Primary Time Oscillator Period, Test Time Base
Oscillator Period, Quiescent Current, Low Voltage Detection level,
TL Sensor Threshold level. Test data reports shall be submitted to
ARRADCOM (6.5).
Switch assembly (Anti-disturbance switch).
4.5.22
4.5.22.1 AD switch function and closure time duration. The
switch assembly shall be placed in an approved fixture. The fixture
shall be capable of rotating the switch assembly through 360 on
its cylindrical axis, while the axis is held at 15 2
referenced to the horizontal, for both CW and CCW directions of
rotation. Verify that the functional requirements of the drawing
are met. This is a non-destructive test and acceptable parts may be
returned to the lot.
4.5.22.2 Insulation resistance of AD switch. The switch
assembly when in a suitable fixture shall be measured for insulation
resistance in the reset position using an approved megohmmeter.
Verify that the switch assembly does meet the requirements of the
drawing. This is a non-destructive test and acceptable parts may be
returned to the lot.
4.5.22.3 Plating of AD switch can. Five (5) cans shall be
randomly selected from each plating batch. The specimens shall be
cross-sectioned through the axial center of the can, polished and
examined microscopically to measure the plating thickness. If the
total average plating thickness for the five cans fails to meet the
requirements as specified on the drawing, the sample shall be
classed defective and the lot shall be rejected. (Destructive test).