| MIL-F-81966(AS)
TABLE 3. (CONT'D)
E.
FINAL ASSEMBLY, ADAPTER, MOUNT MX-8556/AWW-4(V) (DWG. 67A22D1)
CRITICAL - None
AQL 1.0 percent cumulative for all parameters
MAJOR -
101.
Dimensions shall be as specified (Ref. Dwg. 67A22D2)
102.
Adapter shall mate with Power Supply PP-6419/AWW-4(V)
(Ref. Dwgs. 67A22D2, 125AS104, 67A24E12)
103.
Identification plate dimensions and requirements shall be as specified
(Ref. Dwg. 67A22C4)
FINAL ASSEMBLY, ADAPTER, MOUNT MX-9169/AWW-4(V) (DWG. 203AS1OO)
F.
CRITICAL - None
MAJOR -
AQL 1.0 percent cumulative for all parameters
Dimensions of mounting plate and spacers shall be as specified
101.
(Ref. Dwgs. 203AS1O1 and 203AS1O3)
102.
Dimensions of mounting brackets shall be as specified (Ref. Dwg. 203AS1O2)
Identification plate dimensions and requirements shall be as specified
103.
(Ref. Dwg. 203AS1O4)
Spacers must be secured to mounting plate (Ref. Dwg. 203AS1O1)
104.
Adapter shall mate with Power Supply PP-6419/AWW-4(V) and Equipment Rack
105.
MT-38O4/AWW-2A (Ref. Dwgs. 67A35F1, 203AS1O4, 125AS104, 67A24E13)
4.7 Reconditioning of Test Equipment - Equipment which has been subjected to
acceptance and life tests shall be reconditioned by the contractor by replacing all
wear or damaged items. After reworking, the contractor shall resubmit the equipment
for acceptance.
4.8 Presubmission Testing - No item, part or complete equipment shall be
submitted by the contractor until it has been previously tested and inspected by the
contractor and found to comply, to the best of his knowledge and belief, with all
applicable requirements.
4.9 Rejection and Retest - Equipment which has been rejected may be reworked
or have parts replaced to correct the defects and resubmitted for acceptance.
Before resubmitting, full particulars concerning previous rejection and the action
taken to correct the defects found in the original shall be furnished to the
Government Inspector.