FIGURE 7. Guided Weapon Control Group OK-293A/AWW depicting appropriate
vertical and longitudinal axes for shock tests.
4.9 Test procedures. The procedures used for conducting first article
tests and quality conformance tests shall be prepared by the contractor and
made available to the procuring activity (see 6.2.2). The right is reserved
by the procuring activity or the government inspector to modify the tests or
require any additional tests deemed necessary to determine compliance with the
requirements of this specification and the contract (see 6.2.1). MIL-T-18303
shall be used as a guide for preparation of test procedures. When approved
test procedures are available from previous contracts, such procedures shall
be provided and may be used when their use is agreeable to the procuring
activity. However, the right is reserved by the procuring activity to require
modification of such procedures, including additional tests, when deemed
necessary (see 6.2.1).
4.10 Presubmission testing. No item, part or complete equipment shall be
submitted by the contractor until it has been previously tested and inspected
by the contractor and found to comply with all applicable requirements of the
specification and the contract.
4.11 Inspection of packaging. The sampling and inspection of the
preservation, packing, and container marking shall be in accordance with the
rquirements of Section 5.
5. PACKAGING.
5.1 Preservation. Preservation shall be level A or industrial as
specified in the contract (see 6.2.1).