  | ![]() MIL-M-48559A(AR) 
written proposal submitted to the procuring contracting officer 
for evaluation and approval by the Government. When required, the 
contractor shall demonstrate that the effectiveness of the 
proposed alternative(s) is equal to or better than the specified 
quality assurance provisions herein. In cases of dispute as to 
whether the contractor's proposed alternative(s) provide equal 
assurance, the provision of this specification shall apply. All 
approved alternative inspection provisions shall be specifically 
incorporated into the contractor's quality program or detailed 
inspection system, as applicable. 
TABLE I. Requirements and test procedures. 
4.4 Special sampling. 
4.4.1 General. Subsequent to meeting the requirements of 
Table I, three quadrants shall be selected at random by a 
8 
 | 
| 
 