| MIL-M48559A(AR)
apply. When the contractor submits inspection equipment designs
to the Government for approval, he shall give the following
information in his letter of transmittal:
a. The contract number.
b. The contract item (name, model number, etc.).
c. The designs remaining to be submitted and the expected
date of submittal.
6.4 Drawings. Drawings listed in Section 2 of this
specification under the heading US Army Armament, Research
Development and Engineering Center (ARDEC) may also include
drawings prepared by, and identified as Edgewood Arsenal ,
Frankford Arsenal, Rock Island Arsenal, or Picatinny Arsenal
drawings. Technical data originally prepared by these activities
is now under the cognizance of ARDEC.
6.5 Subject term (key word) listing.
Fire control
Mount
6.6 Changes from previous issue. Asterisks are not used in
this revision to identify changes with respect to the previous
issue due to the extensiveness of the changes.
Custodian:
Preparing activityL
Army-AR
Army-AR
(Project No. 1240-A590
16
|