MIL-M-63330 (AR)
6.3.2 Contractor design.  The contractor shall design and
supply inspection equipment compatible with the "Methods of
Inspection" specified in 4.6 of this specification and with the
"Test Conditions" specified in the "General Requirements" of
MIL-STD-81O. Since tolerance of test equipment is normally
considered to be within 10% of the product tolerance for which it is
intended, this inherent error in the test equipment design must be
considered as part of the prescribed product tolerance limit. Thus,
concept, construction, materials and dimensions shall be so selected
and controlled as to insure that the test equipment will reliably
indicate acceptability of a product which does not exceed 90% of the
prescribed tolerance limit and permit positive rejection when
non-conforming.  Construction shall be such as to facilitate routine
calibration of test equipment.
6.3.3 Submission of designs for approval. Contractor designs
shall be approved by the Government prior to fabricating or
procuring the equipment.  Partial submission of inspection equipment
designs is permissible and encouraged. However, the completion date
for design review will be based on the date of the final submission
of designs and the required delivery schedule as stipulated in the
contract.  Submit designs as required to:  Commander, US Army
Armament Research and Development Command, ATTN:  DRDAR-QAF-I, Dover
NJ 07801.
When the contractor submits inspection equipment designs to the
Government for approval, he shall give the following information in
his letter of transmittal:
a.
The contract number
The contract item (name, model number, etc.)
b.
The designs remaining to be submitted and the expected date
c,
of submittal.
6.4 Drawings.  Drawings listed in Section 2 of this
specification under the heading US Army Armament Research and
Development Command (ARRADCOM) may also include drawings prepared
by, and identified as Edgewood Arsenal, Frankford Arsenal, Rock
Island Arsenal or Picatinny Arsenal drawings. Technical data
originally prepared by these activities is now under the cognizance
of ARRADCOM.
Preparing activity:
Custodian:
Army - AR
Army - AR
Project No. 1240-A727
23