| MIL-M-81260A(AS)
ultrasonic, eddy current, x-ray, and liquid penetrants. Particular attention
shall be given to all critical areas. A chart shall be used to summarize con-
ditions for checking individual parts. This chart shall include material spe-
cifications for metals when pertinent to making repairs.
Repair - Instructions for repair, including kitted parts, to
3.5.3.4.6
the extent authorized for intermediate level maintenance shall be provided. Ref-
erence shall be made to the IPB for repair kit details.
3.5.3.4.7
Limits. - A table of acceptable service tolerance limits and
fits shall be provided. The table of limits and fits will serve as a standard and
shall give the plus (+) or minus (-) tolerances that are acceptable to allow con-
tinued operation without affecting the reliability of the component.
3.5.3.4.8
Assembly. - This section shall give essential instructions
for the assembly of component parts into major subassemblies and final assem-
bly of subassemblies to form a complete end item. Assembly instructions
to include all pertinent assembly criteria such as clearances, backlash dimen-
sions, special torque values, peculiar safety wiring, end play and similar data,
shall be provided. Instructions for rigging, adjustment and alignment, when
required, shall be included in logical sequence. Approved corrosion-preventive
compounds, special lubricants, gasket pastes, shall be specified. Instructions
for required assembly lubrication shall be included. Maintenance check re-
quirements (3. 2.4) shall be integrated into the procedure, as applicable. As-
sembly instructions such as "Reverse the disassembly sequence" shall not be
used. Reference to the applicable procedure, for checkout of the item, shall
be made at the end of the assembly instructions.
3.5.3.4.9
Alignment and Adjustment. - Step-by- step procedures de-
scribing required alignment and adjustment resulting from replacement of parts
or assemblies or as required to determine if the component or equipment meets
operational performance standards shall be provided.
3.5.3.4.10
Testing. - Procedures shall contain the intermediate level
instructions for conducting tests of the complete system, component and equip-
ment. Test data pertaining to specific testing conditions, test setup and oper-
ating procedures of applicable GSE shall be included.
3.5.3 .4.10.1
Testing procedures may be omitted if they are identical to
the checkout procedures required in 3.5.3.4.1. In this event, the checkout
29
|