| MIL-P-45969B (AR)
6.5 Submission of results of contractor conducted examinations
and tests. Unless otherwise specified by the contracting officer, the
contractor should forward requested records of examinations or tests
to Commander, ARDEC ATTN: AMSMC-QAF-A (D), Picatinny Arsenal, NJ
07806-5000.
6.6 Process deviation. A process deviation is defined as a
change in the approved basic method of manufacture, or an operational
change which alters the metallurgical or physical properties of the
item.
6.7 Drawings. Drawings listed in Section 2 of this
specification under the heading US Army Armament Research, Development
and Engineering Center (ARDEC) may also include drawings prepared by,
and identified as, Edgewood Arsenal, Frankford Arsenal, Rock Island
Arsenal, Picatinny Arsenal, US Army Armament Research and Development
Command (ARRADCOM) or US Army Armament Research and Development Center
(ARDC) drawings, Technical data originally prepared by these
activities is now under the cognizance of ARDEC.
6.8 Subject term (Key word) listing.
Dry Nitrogen
6.9 Changes from previous issue. Marginal notations are not
used in this revision to identify changes with respect to the
previous Issue due to the extensiveness of the changes.
Preparing activity:
Custodian:
Army-AR
Army-AR
(Project 4933-A033)
27
|