Click here to make tpub.com your Home Page

Page Title: Submission of designs for approval
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 




img
MIL-P-48609 (AR)
6.3.3 Submission of designs for approval. -Contractor
designs shall be approved by the Government prior to fabricating
or procuring the equipment. Partial submission of inspection
equipment designs is permissible and encouraged. However, the
completion date for design review will be based on the date of
the final submission of designs and the required delivery
schedule as stipulated in the contract. Submit designs as
required to Commander, US Army Armament Research and
Development Co-remand, ATTN: DRDAR-QAF-1, Dover, N.J. 07801.
When the contractor submits inspection equipment designs to
the Government for approval he shall give the following
information in his letter of transmittal:
The contract number.
a.
The contract item (name, model number, etc.)
b.
The designs remaining to be submitted and the
c.
expected date of submittal.
6.4 Drawings. -Drawings listed in Section 2 of this
specification under the heading US Army Armament Research and
Development Command (ARRADCOM) may also include drawings
prepared by, and identified as Edgewood Arsenal, Frankford
Arsenal, Rock Island Arsenal or Picatinny Arsenal drawings.
Technical data originally prepared by these activities is now
under the cognizance of ARRADCOM.
Preparing Activity:
Custodian:
Army - AR
Army - AR
Project No. 1240-695
11

Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business