| MIL-P-82442(OS)
3.4.2
Acceleration, ready condition. The pump, mounted as shown
in Figure 1, shall be capable of meeting the performance requirements after
being subjected, in the ready condition, to the accelerations defined in
Table II for a duration of 1 minute for each magnitude. Acceleration is
defined in 6.3.5.
TABLE II
ACCELERATION SCHEDULE
3.4.3
Shock. ready condition. The pump, mounted as shown in Figure 1,
shall be capable of meeting the performance requirements after being
subjected, in the ready condition, to the shock loads defined in Table III.
Shock is defined in 6.3.6.
TABLE XII
SHOCK SCHEDULE
Temperature and humidity.
3.4.4
4
|