4.4.2 Qualification test report. After the contractor completes the
qualification tests, a qualification test report prepared in accordance with
MIL-STD-831 shall be furnished to the qualifying activity.
4.4.3 Qualification test samples for the qualifying activity. Along with
the qua lification test report, the contractor shall submit a sample starter
generator to the qualifying activity.
4.4.4 Qualification tests. Qualification tests shall consist of all
tests described under 4.6 and as specified in table IV, conducted in any
logical order to permit maximum utilization of test facilities:
4.5
Acceptance tests.
Acceptance tests shall consist of the individual
tests.
4.5.1 Individual tests. Each starter-generator shall be subjected to the
following tests, as described under 4.6: