| MIL-S-63348A(AR)
DEFECT
REQUIRE-
INSP
NO.
DEFECT
METHOD
MENT
MAJOR
MINOR
74.
3.3.2.1
Manual
Weapon assembly. Failure to
x
cycle with selector lever set
at AUTO (with selector lever
set on "auto" charge the bolt
with charging handle maintaining
pressure on the trigger: Bolt
shall close when trigger is
pulled.
Charge bolt with charging handle
with trigger released, release
bolt. Pulling of trigger shall
close bolt.
4.5.2.2.4 Accepted weapons. Weapons which have passed all
examinations after successful completion of testinq shall be rubber
stamped by the contractor with the Department of Defense complete
inspection approval stamp on the lower right hand side of the lower
receiver, or the forward face of the magazine well. The Government
representative will control the stamps used for such stampings
required to assure successful completion of all required
examinations and tests.
4.5.2.3 Component parts and concurrent repair parts.
Examination of component parts and concurrent repair parts shall be
performed in accordance with the criteria as specified in the
contract (see 6.1). Examination of these parts shall be
accomplished prior to their assembly into the end item or submission
for acceptance as repair parts.
4.5.2.4 Packaging. Examination of packaging of weapons shall
be performed in accordance with the classification of defects and
acceptable quality level (AQL) specified in Table II.1 Sample
size for each lot shall be in accordance with Inspection Level I of
MIL-STD-105 or a continuous sampling plan of MIL-STD-1235 which will
provide equivalent discrimination. A visual inspection shall be
performed to assure that the criteria specified in the contract (see
6.1) result in the parts and packages meeting the acceptable quality
level, Packages opened for examination shall be repackaged by the
contractor at the contractor's expense (see 6.1).
26
|