| MIL-T-62246B(AT)
4.4 Inspection of production vehicles. The contractor's inspection system shall as a
minimum assure that the vehicle conforms to the physical and dimensional requirements and is
capable of meeting performance requirements contained herein. For each vehicle under contract,
the contractor shall make available to the Government, at the point of final acceptance, records
acceptable to the Government indicating that the servicing and adjusting required by 3.6 have
been accomplished.
5. PREPARATION FOR DELIVERY
5.1 Vehicle processing. The vehicle shall be processed for shipment, from the
manufacturer's plant to the initial receiving activity, in accordance with the manufacturer's
standard commercial practice.
6. NOTES
6.1 Intended use. The vehicles covered by this specification are intended for general
nontactical use by the Government in the performance of the street maintenance tasks indicated.
*
6.2 Ordering data. Acquisition documents should specify the following:
(a)
Title, number and date of this specification.
(b)
Identification of appropriate service for painting and marking (see 3.1.1.1).
(c)
Concealed markings, if required (see 3.1.1.1).
(d)
Rustproofing, if required (see 3.1.1.2).
(e)
Tropical rustproofing, if required (see 3.1.1.2).
(f)
Silicone brake fluid, if required (see 3.1.1.7).
(g)
Gasoline engine, if required (see 3.4.1.2).
(h)
Power plant heaters and a fuel warmer, if required (see 3.4.1.8).
(i)
If a battery heater is not required with power plant heaters (see 3.4.1.8).
(j)
Special transmission requirements (see 3.4.5.1).
(k)
Automatic or semiautomatic transmission, if required (see 3.4.5.2).
(l)
Oil lubricated wheel bearings and axle spindles, if required (see 3.4.9).
(m)
Traction control, if required (see 3.4.9.2).
(n)
Wide base front and rear tires and wheels, if required (see 3.4.10).
(o)
Disc type wheels, if required (see 3.4.10).
25
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |