| MIL-T-6396E
Three 12- by 12-inch samples of composite cell construction.
d.
e. One sample of inner layer ply, without barrier, approximately 900 square
inches in area, including seam.
f.
Two
samples 6- by 6-inch inner layer ply, without barrier.
Three permeability samples as specified in 4.6.12.
g.
h.
One 12- by 12-inch sample of outer ply.
These samples shall not be preplasticized with fluid prior to testing.
TABLE II. Phase I tests (types II and III tanks).
Indicates test applicable
x
Indicates test not applicable
Upon completion of the leakage test, tests may be run in any order desired.
Applies only to oil tanks to be used on aircraft employing an oil dilution
system.
This test applicable to type III tank, only.
This test applicable to type II, class B tanks, only.
4.3.2 Phase II preproduction tests (all types). Phase II preproduction tests
are those tests accomplished on full-scale tanks or portions thereof, at the
descretion of the acquisition activity. The preproduction tests are listed in
table III and described in 4.6. Unless otherwise specified, the tests shall be
conducted in the sequence listed.