4.
4.1 Responsibility for inspection. Unless otherwise
specified in the contract or purchase order, the supplier is
responsible for the performance of all inspection
requirements as specified herein. Except as otherwise
specified, the supplier may utilize his own facilities or
any commercial laboratory acceptable to the Government. The
Government reserves the right to perform any of the
inspections set forth in the specification where such
inspections are deemed necessary to assure supplies and
services conform to prescribed requirements.
4.2 General. Acceptance of the ABTS shall be solely
on the basis of this specification.
4.2.1 Classification. The ABTS shall be classified
as a production model in accordance with paragraph 3.3.5 of
"A model in its final form of final production
MIL-STD-280:
design made by production tools, jigs, fixtures, and
methods. It employs standard parts (or nonstandard parts
approved by the agency concerned)." If it is necessary to
depart temporarily from the mandatory requirements (parts,
processes, etc.) of the technical documents, a form DD 1694
shall be prepared. Minor deviations shall be submitted to
the Navy Technical Representative (NTR) for approval. Major
and critical deviations and waivers shall be submitted to
Naval Air Systems Command for approval in accordance with
the contract. The DD Form 1694 (Request for
Deviation/Waiver) shall be prepared as delineated in
MIL-STD-480 .
4.2.2 Individual items. The ABTS will be accepted
separately and independently of other items of the
AN/AWM-23.
4.2.3 In-process inspection. Prior to entering
acceptance tests, the ABTS shall have completed in-process
inspections.
4.2.4 In-process data. The data resulting from
contractor conducted in-process inspections shall be
presented to the Cognizant Government Inspector (GCI) at the
time the ABTS is offered for Government inspection and
acceptance.
4.2.5 Acceptance test plan. All testing shall be
as specified in the acceptance test plan, as shown in Table
I. Data sheets containing test criteria and measurement
results are a part of the acceptance procedure document.