Critical:
None defined.
4.3.3 Testing.
4.3.3.1 Cavitation (see 3.3) - Major defect - Code No. 02005.
Each lot of warheads, loaded, prior to insertion of the fuze cavity
liner or assembly of the fuze shall be one hundred percent (100%)
subjected to the sequence specified in 4,4.1 using equipment in
accordance with 4.3.4. Units with more than two cracks (3.3.2)
shall be considered defective. Units with pipes (3.3.3) which
appear to widen beneath the surface shall be considered defective.
Units with any oversize surface cavity (3.3.4) shall be considered
defective.
4.3.4 Inspection Equipment.
- Equipment Tabulation ET-
8882186 identifies the inspection
equipment required to perform the
examinations and tests prescribed
in this section. The contractor
shall design inspection equipment
in accordance with the instruc-
tions in paragraph 6.3.
4.3.4.1 Government Rights to Documentation. - Inspection
equipment drawings and lists provided and revised in accordance
with the requirements of the ET may be used by DOD activities for
design, procurement, manufacture, testing, evaluation, production
and receiving inspection, overhaul, shipping, storage, identifica-
tion of stock, ordering and storage of replacement parts, inspec-
tion of items at overhaul, general maintenance of equipment, con-
structions survey and wherever inspection equipment drawings are
needed.
4.4 Test Methods.
|