| ![]() MIL-W-85057(AS)
shall be verified by a maintainability test. The test requiremnets and
procedures shall be prepared by the contractor and submitted to the procuring
activity for approved. The test procedures shall include procedures-end
requirements for adjustments and alignments required at all levels of assembly.
TABLE VI.
ENVIRONMENTAL TESTS REQUIREMENTS
REQUIREMENT
METHOD
PARAGRAPH
PARAGRAPH
TITLE
3.3.9.1, 3.3.9.2
4.6.1.1
Temperature Shock
.
3.3.9.1. 3.3.9.2
4.6.1.2
Temperature-Altitude
3.3.9.1, 3.3.9.4
4.6.1.3
Low Temperature Vibration
3.3.9.3
Humitdy
4.6.1.4
3 .3.9.4
4.6.1.5
Vibration
3.3.9.5
4.6.1.6
Shock
3.3.9.14
4.6.1.7
Gunfire Vibration
3.3.9.13
4.6.1.5
Acoustic Noise
3.3.9.6
4.6.1.9
Salt Spray
3.3.9.6
4.6.1.10
Sand and Dust
3.3.9.9
4.6.1.11
Explosive Atmosphere
3.5.9.7
4.6.1.12
Fungus
3.3.1.5
4.6.1.13
Warm-Up Time
4.6.2.4
Operating Power
4.2.3 Preproduction (First Article) Approval. Approval of the preproduction
sample shall be by the procuring activity upon satisfactory completion of all
tests. No production equipments shall be delivered prior to the approval of
the preproduction sample.
.
.