| as otherwise specified', the supplier may utilize his own facilities or
any commercial laboratory acceptable to the Government. The Government
reserves the right to perform any of the inspections set forth in the
specification where such Inspections are deemed necessary to assure sup-
plies and services conform to prescribed requirements.
Classification of tests - The inspection and testing
4.2
of actuators shall be as-follows:
(a) Qualification tests - Qualification tests are those
tests performed on samples submitted as qualified products to determine
that the item meets all the requirements of this specification.
.
(b) Acceptance tests . Acceptance tests shall be per-
formed on actuators which have been submitted under contract to determine
conformance of the product with requirements set forth in the specifica-
tion -prior to acceptance.
Qualification tests -
4.3
Qualification test sample - The qualification test sample
4.3.1
shall consist of 3 actuators upon which qualification is desired. The manu-
facturer shall furnish all samples.
Tests - The qualification tests shall consist of all the
4.3.2
tests of this specification as described under section on test methods (4.6),"
The tests shall be conducted
on each of the three actuators in the sequence as shown in table I.
Electric motor tests - When electric motors are con-
4.3.3
structed integrally into the actuator, all environmental life tests con-
duced on the assembled actuator are applicable to the motor also. In
addition, motor specification tests such as commutation, dielectric strength,
brush life, locked rotor protection, etc., which are not included in the
required actuator testing, shall be conducted on the motor. Some improvision
of duty cycle or other operating conditions may be necessary to permit de-
termination of all necessary motor characteristics since the specific motor
requirements must meet the actuator specification requirements as well as
the motor specification requirements, Procuring activity approval of the
proposed test program shall be obtained prior to Initiation of the testing.
e