MIL-C-18244A(WEP)
(i) A discussion of any required special functions as as Mach control,
g limiting, etc.
(j) A preedicted reliability of the proposed design, sources of data, and
the analytical approach used in making this prediction and a discussion
of the results in comparison to requirements shall be included.
(k) A preliminary failure analysis of the AFCS.
(l) A general control system layout showing surfaces to be actuated,
method of actuation system duplication, approximate hinge moments,
major components, emergency provisions, etc.
(m) A layout of the hydraulic systems supplying the AFCS. This layout
shall ShOW sources of hydraulic power, pressures required, Peak and
average flow rates, power spectrum, etc.
(n) A schematic wiring diagram of the electrical system affecting the AFCS.
This diagram shall show source(s) Of power, Peak and average power
requirements, voltage, current, etc.
(o) An AFCS control panel outline drawing showing the type switches
USed,
nomenclature and functions available shall be submitted.
3.5.3
Subsystem and Component Specifications - Detailed specifications for subsystems
and components shall be prepared and submitted as engineering information. Specifications shall be
prepared in accordance with Specification MIL-D-18300.
Design Approval Test Specifications - Design approval test specifications and
3.5.4
procedures in accordance with Specification MIL-D-18300 for U.S. Navy aircraft shall be submitted
for approval. Justification shall be submitted for special maintenance and overhaul tools and test
equipment required for these tests.
3.5.5
Automatic Flight Control System Simulation Reports - Reports on simulator test
equipment, test procedures and test results shall be submitted.
Design Approval and Preproduction Test Reports - A report shall be submitted as
3.5.6
engineering inforemation on the design approval and production tests. All test reports shall either
contain or be accompanied by a copy of the applicable test specification.
Identification of Equipment - Assignment of AN nomenclature and approval of
3.5.7
nameplate drawings shall be requested in accordance with Specification MIL-N-18307. AN nomen-
clature may not be required for the following, when approved by the procuring activity.
(a) Approved off-the-shelf equipment which bear the vendor's standard
nameplate and part number,
(b) Approved equipment which when installed becomes a structural part
of the aircraft (i.e. junction boxes, console mounts).
Flight Test Procedures - Flight test procedures for the AFCS shall be submitted
3.5.8
for the approval of the procuring activity.
Preliminary Flight Test Reports - A report shall be prepared and submitted as
3.5.9
engineering information on the preliminary flight test. This report shall discuss any differences
noted between the predicted and actual flight performance.