| MIL-C-38418E(AS)
Vibration error (4.6.8).
d.
e.
Low field strength (4.6.9).
Slaved dynamic accuracy (4.6.10).
f.
Panel lighting (4.6.3.7).
g.
Sampling Plan C - Unless otherwise specified by the procuring
4.5.2.3
activity (as noted in 6.2), 3 samples of each component shall be selected
at random from the first 15 items on the contract and subjected to the
following applicable tests as described under 4.6:
Sampling plan B tests (listed in 4.5.2.2).
a.
Radio noise interference and susceptibility (4.6.11).
b.
c.
Temperature-altitude
(cycling)(4.6.12).
Humidity (4.6.13).
d.
Fungus (4.6.14).
e.
Rain (4.6.15).
f.
Salt fog (4.6.16).
g.
h.
Dust (4.6.17).
Temperature shock (4.6.18).
i.
Leak rate (4.6.18.1).
j.
Vibration failure (4.6.19).
k.
Acoustical noise (4.6.20).
l.
Explosion (4.6.21).
m.
Shock (4.6.22).
n.
Acceleration (4.6.23).
o.
38
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |