| MIL-C-52973A(ME)
where
CFM
=
Cubic feet per minute (free air)
W1
=
Empty weight of capacity check assembly (lb)
W2
=
Full weight of capacity check assembly (lb)
R
=
Air temperature at cooling fan in degrees, Rankine (Fahrenheit,
absolute)
t
= time required to fill reservoir in minutes
= Barometric pressure in inches, Hg
P
Tests shall be in accordance with table II. It is not
4.5.2.2 Test schedule.
required that tests be performed in the order listed, except that the operation
test shall be the last test performed.
Table II.
Test schedule.
4.5.2.3 Test log.
A test log covering the run-in, engine endurance, cycling,
high and low temperature, tilted operation, cleaning procedures and air purity
Storage
test results shall be established tabulating the appropriate test data.
temperature , precipitation, lifting and tiedown, pulling, towing, and pendulum
impact test as applicable, shall also be recorded in this log.
4.5.2.4 Test condtions.
a.
Unless otherwise specified herein, sequence of tests is optional with
the tester.
b.
Only that maintenance established by the contractor and submitted as
maintenance schedule prior to start of testing shall be perfomed
during the test.
Safety and human factor considerations shall be evaluated throughout
c.
testing.