| MIL-C-70498(AR)
Conduct the vibration test with the
4.6.2 ESS vibration.
interconnect positioned on an appropriate adapter affixed to a
vibrating machine that is capable of providing the amplitudes and
frequencies specified in 3.3.3. unless otherwise specified, the
test equipment shall be in accordance with the "Test Facilities"
requirements of MIL-F-13926. The applied motion shall be in two
separate planes for the time period specified. Upon completion of
the vibration sweep the interconnect shall be removed from the
vibration adapter and shall be subjected to the test in 4.6.3. It
shall meet the requirements of 3.2.1.
4.6.3 Functional tests. This test is to be conducted
utilizng a certified Ohm meter. Measure the resistance between
the connector contacts listed in Table II. All measures
resistances shall meet the requirements of 3.2.1.
The interconnect shall be subjected to a
4.6.4 Workmanship.
visual and tactile examination for evidence of faulty
workmanship. The assembly shall conform to the requirements of
3.6.
4.7 Reliability testing. The requirement for reliability
test approval and the responsibility (Government or contractor)
for reliability testing shall be as specified in the contract.
The sample for reliability test shall consist of 3 interconnects.
The samples shall be manufactured in the same manner, using the
same materials, equipment, processes, and procedures as will be
used in the production of the balance of the contract quantity.
All parts and materials, including packaging and packing shall be
obtained from the same source of supply as will be used in the
production of the balance of the contract quantity.
4.7.1 Government testinq. When the Government is responsible
for conducting reliability tests, the contractor prior to
submitting the sample to the Government, shall inspect the sample
to assure that it conforms to all requirements of the contract and
submit a record of this inspection with the sample, including
certificates of conformance for all materials.
4.7.2 Contractor testinq. When the contractor is responsible
for conducting reliability tests, the sample shall be inspected
and tested by the contractor for all the requirements of the
contract. The sample and a record of these inspections and tests,
including certificates of conformance for all materials, shall be
submitted to the Government for approval.The Government reserves
the right to witness any or all of the contractors reliability
tests and inspections.
15
|