| ![]() MIL-C-70501 (AR)
Arsenal, Rock Island Arsenal or Picatinny Arsenal drawings.
Technical data originally prepared by these activities is now
under the cognizance of ARDC.
6.5 Additives.
Additives shall have prior approval by the
Contracting Officer.
Mold release agents and processing aids
are considered additives.
6.6 Hangup. For this specification, the meaning of a
"hangup" is a round which is dropped into the mortar tube but
does not strike the firing pin with enough force to function
the primer.
6.7 Submission of formal proving ground firing report.
Residue test data shall be sent to Commander, US Army Armament
Research and Development Center, ATTN: DRSMC-QAT-B(D), Dover,
NJ 07801.
6.8
Proving ground test summary
Test
Sample Size
Requirement
Residue Test
350 Containers
Absence of
(First Article)
(175 test rounds,
hangup, secondary
25 reference rounds
flame, & flaming
debris, zone 4
Residue Test
125 Containers
Absence of
(Production)
(50 test rounds)
Hangup, secondary
flame, & flaming
debris, zone 4
6.9 Data requirements.
Deliverable data required by this
specification and not referenced elsewhere are cited below.
Data shall be furnished to DRSMC-QAT-B(D), ARDC, Dover, NJ
07801.
Paragraph
Data Requirement
Applicable DID
3.11
Process Description
DI-P-1604
4.5.4
Test & Demonstration Reports
DI-T-1906
Custodian:
Preparing activity:
ArmyAR
Army-AR
(Project 1310-A350)
23
|