| MIL-G-82455(OS)
Date of tests and names of persons conducting test
(a)
(b)
Run or test plan used
Serial number or identification number of the Generators
(c)
Test results of the periodic production tests.
(d)
4.4.2.1.2.1
4.5.2.1
Vibration
4.4.2.1.3
4.5.2.2
Shock
4.4.2.2
4.5.2.3
Leakage
4. 5.2.4 Function tests. - The Generator shall be subjected to the
function test of 4.4.2.3 at room ambient temperature with the longitudinal
axis in the horizontal plane
4.5.3
Periodic production test equipment.- The following items of
test equipment or equivalent will be required to perform the periodic
production tests:
(a) See 4.4.3(a)
(b) See 4.4.3(b)
(c) See 4.4.3(e)
(d) See 4.&.3(f)
Acceptance inspection consists of
4.6
Acceptance inspection.-
two parts, as follows:
(a) Examination
(b) Lot acceptance tests
Acceptance sampling.-
4.6.1
Examination. -
The acceptance examinations shall be
4.6.1.1
conducted on each Generator to be delivered.
4.6.1.2 Lot acceptance. - Unless otherwise specified in the
contract or order, a random sample of Generators shall be selected
from each inspection lot for the testing required for lot acceptance
(see 4.6.2.2). The size of this sample shall conform to the require-
ments of Standard MIL-ST9-105 for an Acceptance Quality Level (AQL) of
0.25%, except the sample size shall never be less than 37 Generators.