4.1.5 Classification of inspections. The inspection requirements
specified herein are classified as follows:
First article inspection (see 4.3)
a.
Quality conformance inspection (see 4.2)
b.
4.1.6 First article inspection report. After completion
of the first article inspection, the contractor shall prepare and make
available a test report for procuring activity acceptance (see 6.2.2).
4.2 Quality conformance inspection. Each production gun system shall be
subjected to the quality conformance inspection in Table 111.
TABLE III. Quality conformance inspection.
Examination
Requirement
First
Quality
or test
article
conformance
Examination or test
paragraph
x
4.2.l(a)
x
3.1.1
Major component list
x
x
4.2.3.1
3.1.3
Input electrical power
4.2.3.2
x
x
3.1.4
Input pneumatic power
x
4.2.3.3
x
3.2.1.1
Dispersion and accuracy
4.2.3.4
x
3.2.1.2
x
Firing rates
x
x
4.2.3.5
3.2.1.3
Clearing
4.2.3
x
x
3.2.1.4
Burst firing schedule
4.2.3.6
x
x
3.2.1.5
Gun system signals
4.2.3.7.1
x
x
3.2.1.6.1
Breakaway torque
x
4.2.3.7.2
x
3.2.1.6.2
Running torque
x
4.2.2
3.2.2
x
Weight
x
4.3.2
Reliability
3.2.3
x
4.3.1
3.2.4
Durability
x
x
4.2.l(b)
Production drawings
3.3.1
x
x
4.2.l(b)
Standards of manufacture
3.3.2
x
4.4
x
Interchangeability
3.3*3
x
x
Workmanship
3.5
4.2.1(c)
x
4.5
x
Packaging
5
4.2.1 Visual examination.
Each production gun system shall be visually
examined to assure:
The major components identified in 3.1.1 were previously accepted
a.
and were not damaged during assembly.
The system is assembled in accordance with the drawings, parts lists
b.
and other documents listed on Drawing 1395AS1OO as specified in
3.3.1 and 3.3.2.
c.
Workmanship is in accordance with the requirements of 3.5.
10
|