| ![]() MIL-H-48620(AR)
When the contractor submits inspection equipment designs to the
Government for approval, he shall give the following information in
his letter of transmittal:
a. The contract number
b. The contract item (name, model number, etc.)
c. The designs remaining to be submitted and the expected date
of submittal.
6.4 Drawings. - Drawings listed in Section 2 of this specifie-
cation under the heading US Army Armament Research and Development
Command (ARRADCOM) may also include drawings prepared by, and
identified as Edgewood Arsenal, Frankford Arsenal, Rock Island
Arsenal or Picacinny Arsenal drawings. Technical data originally
prepared by these activities is now under the cognizance of ARRADCOM.
Custodian:
Preparing Activity:
Army - AR
Army - AR
Project No. 1240-A723