| ![]() MIL-M-70779 (AR)
APPENDIX A
40.2.3 Self-destruct time out. The self-destruct time out shall be
tested by connecting the S.U.T. as shown in Figure 3. Input
shall have
pulses applied at a rate consistent with the overall testing time desired and
the output shall be observed at F.
Figure 3.
Self-destruct time out measurement.
TEST SEQUENCE:
1. Connect S.U.T. as shown in Figure 3.
turn on time shall be as specified in paragraph 3.4.
2.
3. PUlse generator shall start when
at a convenient repetition
rate. The pulse generator shall have a duty cycle of 30% to 70%.
4. Output shall switch from a logic high
to a logic low (GND) after
32,000 input counts:
NOTE: If time out is measured by time rather than counts, then the limit
shall be 0.1%.