| MIL-N-81207A(AS)
approval of material during the course of manufacture shall not be
construed as a guarantee of the acceptance of the finished
product. Acceptance tests shall consist of the following:
(1) Individual Tests
(2) Sampling Tests
(3) Reliability Assurance Tests
(4) Special Tests
Individual Tests - Each equipment submitted for
4.4.1
acceptance shall be sub jetted to the individual tests. These
tests shall be adequate to determine compliance with the
requirements of material, workmanship, operational adequacy and
reliability. As a minimum, each equipment accepted shall have
passed the following tests:
(1) Examination of Product
(2) Operational Test
(3) Manufacturing Run-In Test
Examination of Product - Each equipment shall
4.4.1.1
be examined carefully to determine that the material and
workmanship requirements have been met.
Operational Test - Each equipment shall be
4.4.1.2
operated long enough to permit the equipment temperature to
stabilize and to check sufficient characteristics and record
adequate data to assure satisfactory equipment operation.
Manufacturing Run-In Test - Each equipment
4.4.1.3
shall be operated under the conditions specified herein for a
period of 10 hours without failure. A failure shall be defined as
anything which causes malfunctioning of the equipment. Only those
adjustments will be permitted which can be made by using such
controls and adjustments that are accessible to the operator
during the normal use of the equipment. This test shall be
deleted if the reliability test includes a test on each equipment
which consumes at least 10 hours of operation.
58
|