4 .5.4
The part function
(3)
(4) Name of the manufacturer
(5) Nature of the failure
(6) The number of hours which the part operated
prior to failure
Failure Report - In the event of a failure, the
4.5.4.1
procuring activity shall be notified. A report shall be submitted
to the procuring activity upon completion of the test. In this report
the contractor shall propose suitable and adequate design or material
corrections for all failures which occurred. The procuring activity
will review such proposals and determine whether they are acceptable.
Reconditioning of Life Test Samples - An equipment
4.5.5
which has been subjected to the life test shall be reconditioned as
follows:
(1) On completion of the life test, the
equipment
shall be reworked by the contractor
by replacing
all "wear" items. The "wear" items
shall be
determined by agreement between the
contractor
and the procuring activity.
(2) After reworking, the contractor shall resubmit
the equipment for acceptance.
Test Procedures - The procedures used for conducting
4.6
preproduction tests, acceptance tests and life tests shall be prepared
by the contractor and submitted to the proctoring activity for review
and approval. The right is reserved by the procuring activity or the
government inspector to modify the tests or require any additional
tests deemed necessary to determine compliance with the requirements
of this specification or the contract. MIL-T-18303 shall be used as a
guide for preparation of test procedures. When approved test procedures
are available from previous contracts such procedures will be provided
and may be used when their use is approved by the procuring activity.
However, the right is reserved by the procuring activity to require
modification of such procedures, including additional tests, when deemed
necessary.