| MIL-N-81497A(AS)
Reconditioning of Tested Equipment - Equipment which
4.7
has been subjected to acceptance and life tests may be reconditioned by
the contractor by replacing all worn or damaged items. After reworking
the contractor shall resubmit the equipment for acceptance.
4.8
Presubmission Testing - No
item, part or complete
equipment shall be submitted by the contractor
until it has been pre-
viously tested and inspected by the contractor
and found to comply, to
the best of his knowledge and belief, with all
applicable requirements.
Rejection and Retest - Equipment which has been rejected
4.9
may be reworked or have parts replaced to correct the defects and resub-
mitted for acceptance. Before resubmitting, full particulars concerning
previous rejection and the action taken to correct the defects found in the
original shall be funished the government inspector.
PREPARATION FOR DELIVERY
5.
5.1
General - All major units and parts of the equipment shall
be preserved, packaged, packed and marked for the level of shipment specified
in the contract or order in accordance with MIL-E-17555 and MIL-STD-794. In
the event the equipment is not covered in Specification MIL-E-17555, the
method of preservation for Level A shall be determined in accordance with
the selection chart in Appendix D of MIL-STD-794.