Acceptance Tests:
4.4
The contractor shall furnish all samples and shall be
responsible for accomplishing the acceptance tests. All
inspection and testing shall be under the supervision of the
government inspector. Contractors not having testing
facilities satisfactory to the procuring activity shall engage
the service of a commercial testing laboratory acceptable to
the procuring activity. The contractor shall furnish test
reports showing quantitative results for all acceptance tests.
Such reports shall be signed by an authorized representative
of the contractor or laboratory, as applicable. Acceptance or
approval of material during the course of manufacture shall
not be construed as a guarantee of the acceptance of the
finished product. Acceptance tests shall consist of the fol-
lowing:
(1) Individual Tests
(2) Sampling Tests
(3) Special Tests
Individual Tests:
4.4.1
Each equipment submitted for acceptance shall be subjected to
the individual tests. These tests shall be adequate to
determine compliance with the requirements of material, work-
kmanship, operational adequacy and reliability. As a minimum,
each equipment accepted shall have passed the following tests:
(1) Examination of Product
(2) Operational Test
(3) Manufacturing Reliability Test
Examination of Product:
4.4.1.1
Each equipment shall be examined carefully to determine that
the material and workmanship requirements have been met.