4 .4.3 Testing. The following tests shall be performed using
MIL-STD-105 for sampling plan requirements unless otherwise
specified.
4.4.3.1
Moisture content
(See Table II) - Major defects.
TABLE II
The contractor shall provide adequate controls to insure the
materials comply with the requirement. For verification, the
contractor shall select and subject to test, one sample of each
material from each eight hours production. A composite sample shall
not be used. If the moisture content of a sample exceeds the
requirements and loading has not begun, the material represented by
the sample shall be rejected. If components have been loaded with a
material containing excess moisture, the remaining unloaded material
and the loaded components shall be rejected. Test procedures shall
be as specified in 4.5.1.
4.4.3.2 Functioning. The signal assemblies shall be observed
for any evidence of failure to comply with the requirements as
classified in Table III when tested as specified in 4.5.2.
TABLE III