Click here to make tpub.com your Home Page

Page Title: Submission of contractor designs
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 




img
6.3.5 Submission of contractor designs. - All submitted
designs shall contain a reference to the applicable five digit
Code Number contained in Section 4 of this specification.  Unless
otherwise specified on the (EL) Equipment List, all designs of
equipment for inspection of defects classified as critical and
major shall be submitted for approval to the Commanding Officer,
Picatinny Arsenal, ATTN:  SMUPA-ND9.  All other designs of inspection
equipment shall be approved by the inspection element of the agency
administering the contract; submission shall be as directed by
the contracting officer.  Partial submission of inspection equip-
ment designs is permissible and encouraged.  However, the Arsenal
completion date for design review will be based on the date of
the final submission of designs.  Picatinny Arsenal design review
will be accomplished normally within one month after receipt.
6.4 Submission of First Article Samples. - Instruction as
to the location for the evaluation of the First Article sample
shall be obtained from the Contracting Officer.  Upon receipt
of such request, the Contracting Officer shall advise Picatinny
Arsenal and instructions will be issued accordingly.  All inquir-
ies should be forwarded to:  Commanding Officer, Picatinny Arsenal,
ATTN:  SMUPA-NI.
6.5 Defect Reporting. - Beginning with the first lot and
continuing until 25 lots have been produced and accepted by the
Government, the contractor shall submit a defect report to the
Commanding Officer, Picatinny Arsenal, Dover, New Jersey, ATTN:
SMUPA-ND9.  After 25 lots have been produced and accepted, the
contractor shall submit a defect report for every fifth lot for
the remainder of the contract.  The defect report shall contain the
results of the inspections and tests as per paragraphs 4.3.2 and
4.3.3 of this specification,  The inspections and tests shall be
identified in the report by Defect Code Numbers as shown In para.
4,3.2 and 4.3.3.
.
NOTICE:  When Government drawing, specifications, or other data are
used for any purpose other than in connection with a definitely re-
lated Government procurement operation, the United States Government
thereby incurs no responsibility nor any obligation whatsoever: and
the fact that the Government may have formulated, furnished, or in
any way supplied the said drawings, specifications, or other data is
not to be regarded by implication or otherwise as in any manner licen-
sing the holder or any other person or corporation or conveying any
rights or permission to manufacture, use, or sell any patented inven-
tion that may In any way be related thereto.
Preparing Activity:
Custodian:
Army - MU
Army - MU
Project No. 1340-
15

Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business