Click here to make tpub.com your Home Page

Page Title: Manufacture of environmental test items
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 




img
MIL-I-85889(AS)
4.2.3.7 Configuration management plan. When specified in the contractor order, the contractor shall prepare
a configuration management plan covering Phases II and III of the development program. acceptance authority
shall be as specified herein (see 4.35 and 4.4.5). The plan shall be made available to the contracting activity for
acceptance no later than 30 days prior to the Preliminary Design Review.
4.2.3.8 Development specification. When specified in the contract or order, the contractor shall prepare a
Type B2, Critical Item Development Specification in accordance with MIL-STD-490 defining performance, design,
development and test requirements for the igniter. The specification shall be developed according to the format
specified in MIL-STD-961. The development specification shall be made available to the contracting activity no
later than 30 days prior to the Preliminary Design Review.
4.2.3.9 WSESRB data package. When specified in the contract or order, the contractor shall prepare a Weapon
System Explosives Safety Review Board (WSESRB) data package in accordance with NAVAIRINST 5100.7 The
data package shall provide background information supporting the planned system safety program. The data package
shall be made available to the contracting activity no later than 30 days prior to the Preliminary Design Review
4.2.3.10 WSESRB presentation. When specified in the contract or order, the contractor shall prepare a Weapon
System Explosives Safety Review Board (WSESRB) presentation in accordance with NAVAIRINST 5100.7. The
presentation shall be made to the WSESRB to obtain concurrence that the planned program satisfies current Navy
requirememts. The presentation shall be given to the WSESRB no later than 30 days prior to the Preliminary Design
Review.
4.2.3.11 Review agenda. When specified in the contract or order, the contractor shall provide the agenda for
the Preliminary Design Review. The agenda shall set forth the place time, date, purpose, and objectives of the
review. The agenda shall be made available to the contracting activity no later than 30 days prior to the Preliminary
Design Review.
4.2.3.12 Preliminary Design Review. At the conclusion of the Phase I effort and when specified in the contract
or order, the contractor shall conduct a Preliminary Design Review in accordance with MlL-STD-1521. Upon
satisfactory completion of the Preliminary Design Review, the contracting activity will authorize initiation of Phase II.
4.2.3.13 Review minuts. When specified in the contractor order, the contractor shall prepare a record of the
results of the Preliminary Design Review. A draft copy of the review minutes shall be made available to the contracting
activity for review and comment no later than 30 days following the review. The final review minutes shall be distributed
no later than 15 days after receipt of the contracting activity's comments.
4.3 Phase I - Design Verification.
4.3.1 Fabrication.
4.3.1.1 Manufacture of environmental test items. The contractor shall manufacture test units in accordance
with the approved Level 2 drawings
4.3.1.2 Manufacture of inert test items. The contractor shall manufacture inert test items which replicate the
mass properties of the live Type II igniter. The number of test items will be specified in the contract (see 6.2.1).
These test units will be employed for handling and container tests.
14

Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business